Data center moratorium discussion
Summary
Residents and Councilwoman Sadrakula say the three data centers already in Clifton are driving up electric bills, straining water and power, and bringing noise. A five-year moratorium on new data centers was proposed, with legal noting an ordinance amendment is required.
At a glance
- Total mentions
- 3
- Last 30 days
- 0
Last discussed Aug 5, 2026.
Impact analysis
Residents say data centers account for a large share of rising electricity costs; the city also weighs lost tax revenue versus utility strain.
Residents would see relief from rising electric bills and environmental strain if a moratorium passes.
Data center developers and property owners seeking new projects would be blocked during a moratorium.
Mentions & discussions (2)
City Council - Aug 5, 2026
Clifton banned new data centers, betting that lost development opportunities are minimal since few suitable properties exist and that energy/water demands outweigh the tax upside. The ordinance can be revisited as state policy evolves.
City Council - Jul 7, 2026
Residents and Councilwoman Sadrakula say the three data centers already in Clifton are driving up electric bills, straining water and power, and bringing noise. A five-year moratorium on new data centers was proposed, with legal noting an ordinance amendment is required.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Clifton
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.