The Residences at Sterling Pointe Phase 2 — second 30-unit building
Description
The applicant sought amended site plan approval to build the second of two 30-unit apartment buildings, delayed since 2023 by water-allocation disputes. The first building is under construction and expected to be occupied by February 2027.
Impact summary
Adds 30 more senior apartments to Somerset as the final phase of the 136-home Sterling Pointe development; Building One opens around February 2027.
Applicant
- Name
- Cal-Sterling Franklin, LLC
- Address
- Spangenberg Lane, Somerset, NJ (Block 507.40, Lot 2)
At a glance
- Hearings
- 2
- Public comments
- 1
- Total mentions
- 2
Last vote · Planning Commission
Discussed at 1 meeting in the last 60 days; most recently Oct 7, 2026.
Meeting timeline (2)
Franklin Township Planning Board Meeting - Oct 7, 2026
The board formally approved construction of the second 30-unit apartment building at the Sterling Pointe senior community, after years of water-supply delays.
Franklin Township Planning Board Meeting - Aug 5, 2026
Preliminary and final major site plan approval with a conditional-use variance to construct a second 30-unit apartment building in the SCV zone.
Related issues (1)
We'll email you when it's on an upcoming agenda, when it's voted on and when its status changes, at most once a day.
The weekly brief for Franklin Township
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.