Pennsauken Community Center Progress

Summary

The audio-visual and paging contractor at the new library/municipal complex got a third change order of $52,111, pushing the contract to $507,810 — total changes now exceed 20% of the original award.

At a glance

Total mentions
4
Last 30 days
0

Last discussed Jul 16, 2026.

Impact analysis

💰Financial impact

Adds $52,111 to a contract that has grown from $359,478 to $507,810.

✅Who benefits

Library and municipal complex users will get functioning AV and paging systems.

⚠️Who could be affected

Pedestrians, including children, walking along the route between Cove Road and the complex lack a safe path.

Mentions & discussions (5)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Pennsauken

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.