Civic Issues
Topics getting the most attention in Pennsauken public meetings, ranked by how frequently they are discussed.
2 issues in development with high priority
Pennsauken Community Center Progress
The audio-visual and paging contractor at the new library/municipal complex got a third change order of $52,111, pushing the contract to $507,810 — total changes now exceed 20% of the original award.
Redevelopment study near Pennsauken Transit Center
Several underused properties near the Transit Center are being studied as a possible 'Area in Need of Redevelopment' — the first step toward new housing, jobs, and investment there. The designation would be non-condemnation, meaning no eminent domain.